Construction timeline
2024.12.15

Foundation Stone Laying
2025 Q1

Contractor Procurement Procedure
2025 Q1

Contract Signing
2025 Q1

Site Handover
2025 Q1

Construction Area Setup
2025 Q1

Landscaping
2025 Q1

Excavation of Foundation Trenches
2025 Q2

Pouring of Strip Foundations
2025 Q2

Waterproofing and Slab Foundation
2025 Q2

Basement Walls
2025 Q2

Ceiling Above the Basement
2025 Q2

Ground Floor Walls
2025 Q2

Ceiling Above the Ground Floor
2025 Q2

Upper Floor Walls
2025 Q3

Upper Floor Slab
2025 Q3

Bell Tower
2025 Q3

Roofing of the Church's Truss Structure
2025 Q3

Placement of CLT Panels
2025 Q3

Formation of Slope Layering System
2025 Q3

Partition Walls
2025 Q3

Floor Preparation
2025 Q3

Mechanical Engineering Base Installations
2025 Q4

Plastering
2025 Q4

Green Roof Construction
2025 Q4

Facade Insulation
2025 Q4

Interior Doors and Windows
2025 Q4

Cold and Hot Flooring
2026 Q1

Interior Wall Cladding
2026 Q1

Painting and Varnishing
2026 Q1

Interior Design Works
2026 Q1

Sidewalks, Parking Lot
2026 Q1

Landscaping Works
2026 Q2

Church Consecration