Construction timeline

2024.12.15
Foundation Stone Laying
2025 Q1
Contractor Procurement Procedure
2025 Q1
Contract Signing
2025 Q1
Site Handover
2025 Q1
Construction Area Setup
2025 Q1
Landscaping
2025 Q1
Excavation of Foundation Trenches
2025 Q2
Pouring of Strip Foundations
2025 Q2
Waterproofing and Slab Foundation
2025 Q2
Basement Walls
2025 Q2
Ceiling Above the Basement
2025 Q2
Ground Floor Walls
2025 Q2
Ceiling Above the Ground Floor
2025 Q2
Upper Floor Walls
2025 Q3
Upper Floor Slab
2025 Q3
Bell Tower
2025 Q3
Roofing of the Church's Truss Structure
2025 Q3
Placement of CLT Panels
2025 Q3
Formation of Slope Layering System
2025 Q3
Partition Walls
2025 Q3
Floor Preparation
2025 Q3
Mechanical Engineering Base Installations
2025 Q4
Plastering
2025 Q4
Green Roof Construction
2025 Q4
Facade Insulation
2025 Q4
Interior Doors and Windows
2025 Q4
Cold and Hot Flooring
2026 Q1
Interior Wall Cladding
2026 Q1
Painting and Varnishing
2026 Q1
Interior Design Works
2026 Q1
Sidewalks, Parking Lot
2026 Q1
Landscaping Works
2026 Q2
Church Consecration